Located in Scheduling, Labor Projections (also called Worker Loading) help teams quickly estimate the labor needed for active projects. Projections can be broken down by labor type, such as trades, crafts, or specialties.
Labor Projections
Header information
Budgeted Hours
Pulled from the Budgeted Labor Hours field on the Job Detail page, or from the Job > Budgets page (if importing budgets from the ERP).
Actual Hours
Pulled from the sum of the Actual Hours column on the Job Detail > Budgets page (if importing actuals from the ERP).
Projected Hours Left
Pulled from the Projected Hours column on the Job Detail > Budgets page.
Remaining Hours
Calculated as:
Budgeted Labor Hours − Actual Hours − Remaining Projected Hours
(This represents the remaining worker hours needed after the last data refresh.)
Customer Name
When projecting the labor needed on a job, users can use the Initialize button on this page to quickly load the labor needed for that job.
Begin Date
Date will default to the Job Begin Date. If that date is in the past, it defaults to today's date
End Date
Defaults to the Job End Date
Labor Type
Choose the type of labor needed (e.g., Electrical, Plumbing, Roofing, etc.)
Distribute By (Hours or Bulk Add Workers)
Hours
With this option selected, users will need to select how they want to spread hours across the job dates.
Hours to Distribute
Pulled from the job’s Budgeted Labor Hours minus already distributed hours.
Distribution
Hours can be evenly spread, be front-weighted, or back-weighted
Rounding Options
Worker counts can be rounded down to the nearest whole worker or rounded up the highest whole worker
Bulk Add Workers
With this option selected, users only need to enter a set number of workers they want each work day across the dates selected
Once the Labor Type row has been added, the projected worker counts can be manually adjusted as needed. This page will also show the number of workers that have been assigned on the Daily Scheduling page so users can quickly see if they need to schedule additional workers.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article