Labor Projections (also called Worker Loading) help teams quickly estimate the labor needed for active projects. Projections can be broken down by labor type, such as trades, crafts, or specialties.
Job Projections
Header information
Budgeted Hours
Pulled from the Budgeted Labor Hours field on the Job Detail page, or from the Job > Budgets page (if importing budgets from the ERP).
Actual Hours
Pulled from the sum of the Actual Hours column on the Job Detail > Budgets page (if importing actuals from the ERP).
Projected Hours Left
Pulled from the Projected Hours column on the Job Detail > Budgets page.
Remaining Hours
Calculated as:
Budgeted Labor Hours − Actual Hours − Remaining Projected Hours
(This represents the remaining worker hours needed after the last data refresh.)
When projecting the labor needed on a job, users can use the Initialize button on this page to quickly load the labor needed for that job.
Begin Date
Date will default to the Job Begin Date. If that date is in the past, it defaults to today's date
End Date
Defaults to the Job End Date
Labor Type
Choose the type of labor needed (e.g., Electrical, Plumbing, Roofing, etc.)
Distribute By (Hours or Bulk Add Workers)
Hours
With this option selected, users will need to select how they want to spread hours across the job dates.
Hours to Distribute
Pulled from the job’s Budgeted Labor Hours minus already distributed hours.
Distribution
Hours can be evenly spread, be front-weighted, or back-weighted
Rounding Options
Worker counts can be rounded down to the nearest whole worker or rounded up the highest whole worker
Bulk Add Workers
With this option selected, users only need to enter a set number of workers they want each work day across the dates selected
Once the Labor Type row has been added, the projected worker counts can be manually adjusted as needed. This page will also show the number of workers that have been assigned on the Daily Scheduling page so users can quickly see if they need to schedule additional workers.
Global Projections
Employees
Displays daily or weekly worker counts for employees whose Position is set to Short-Term Scheduling or Both.
Can be filtered by Labor Type or Resource Business Group
Totals (assigned / projected)
Left side shows assigned employees (from Daily Scheduling)
Right side shows projected worker counts (from labor projections)
Both totals can be filtered by Labor Type or Job Business group
Difference (assigned / projected)
Left: Difference between actual employee count and assigned employees.
Right: Difference between employee count and projected worker needs.
Job Projections Grid
The grid displays:
Job-level labor projections per Labor Type
Assigned employees (from Daily Scheduling)
This gives a high-level comparison between:
Projected labor needs
Actual worker availability
Current daily/weekly schedules
Use filters to model what-if labor scenarios, such as borrowing employees from other Business Groups. This helps users evaluate staffing options across the organization before making actual scheduling changes.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article