Understanding the Method Column:
The Method column determines how the system calculates remaining Hours and Cost in the Cost Projections grid.
When using unit-based projections, Remaining Projected Units are the starting point. Based on the selected Method, the system uses the appropriate rates to calculate the remaining Hours and Cost.
For example, if 100 units remain and the selected Method uses 2 hours per unit, the system calculates 200 Remaining Projected Hours.
Method Options
Default Method
The system automatically assigns a Method based on the budget code's % Units Complete:
Budget — Less than 10% complete
Actual — 10% complete or more
Override — Used when the previous month's projection was set to Override
Users can change the Method when needed.
How Each Method Affects Projections
Budget
Uses the rates from the Current Estimate to calculate remaining Hours and Cost.
Actual
Uses rates calculated from Actuals to Date to calculate remaining Hours and Cost.
Override
Allows users to manually enter the values used for the remaining projection when the Budget or Actual rates don't accurately reflect the expected work.
Enable the Method Column
Admins can enable the Method column from:
Admin > Projection Categories > Column Settings
When enabled:
Remaining Projected and Total Projected sections become read-only.
The Recalculate button appears in the upper-right corner of the grid.
Selecting Recalculate updates projection values based on the selected Method.
For more information, see Projection Setup.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article